SALALAH : The Ministry of Transport, Communications and Information Technology is intensifying efforts to implement and maintain a series of developmental road projects in Dhofar Governorate. These initiatives aim to enhance infrastructure efficiency and prepare for the upcoming Khareef (monsoon season), facilitating smoother tourist, economic, and social mobility.

The ongoing works include road dual-carriageway, development, paving, maintenance, and connectivity projects linking various wilayats of Dhofar.
Eng. Said Mohammed Tabook, Director General of Roads and Land Transport in Dhofar, stated that the Ateen Tunnel project in Salalah has achieved significant progress, with completion reaching 93%—23% ahead of schedule. This is expected to alleviate traffic congestion during the Khareef season. Meanwhile, the dual-carriageway of Sultan Taimour Street (6.8 km) in Al Saada area is 40% complete, and Al Farooq Street dual-carriageway (7.6 km) has reached 45%.
Read More
- SalamAir resumes direct Muscat–Beirut flights
- His Majesty Sultan Haitham issues Royal Decrees on national symbols, facility protection and multinational tax
- Oman opens Muscat Airport office to protect arriving workers from exploitation and trafficking
- Misleading health ads in Oman could draw RO 1,000 fines, licence suspension or cancellation
- Muscat Expressway works to begin by November; changes to office hours under study

He added that the Ministry is implementing the Mughsail Road and Bridge project in Salalah (20% complete), featuring a 12-meter-high concrete bridge, parking areas, a pedestrian walkway with lighting, and a ground crossing serving tourist sites. The Raysut-Mughsail dual-carriageway road (33 km) includes six overpasses/underpasses, roundabouts, and animal crossings, alongside linking the 18 November Road to the dual-carriageway section (5.5 km).

In the Wilayat of Al Mazyunah, the Harweeb-Al Mazyunah-Maitin road project (210 km) is approximately 65% complete, divided into four main segments. Additionally, the Andat-Habrut road (10 km) is underway.
In the Wilayat of Maqshin, the asphalt network project (170 km) is 58% complete, connecting Marsudid, Al Manadir, Mandar Al Dhabyan, and Al Mashash areas, with completion targeted for June 2026.
The Ministry is also progressing on the Seeh Al Kheerat-Shisr road in Thumrait (46 km), in collaboration with the Najd Agricultural Area Development Office. This vital route passes through key agricultural zones and is slated for completion by October 2026. Additionally, the tender for improving Al Shuwaimiyah Pass on the Shaleem-Al Shuwaimiyah road (2.5 km) in Shaleem and Halaniyat Islands has been awarded, featuring drainage channels, protective barriers, and road signage.

He noted that construction has begun on the third, fourth, and fifth phases of Sultan Said bin Taimour dual-carriageway road (nearly 400 km), with a total cost exceeding RO 258 million. Last month, the new Arqut-Sarfait Mountain Road (13.5 km) was inaugurated, enhancing connectivity between the wilayats of Rakhyut and Dhalkut and extending to the Sarfait border crossing with Yemen.