MUSCAT : The Director of Water Networks in the Wilayat of Al Mudhaibi confirmed that the completion rate of the water distribution network project in the North Al Sharqiyah Governorate has reached 48% so far, which is more than 11% ahead of the planned rate. The project is one of the important ones that are currently being implemented in the state, under the supervision of the Oman Water and Wastewater Services Company, and on behalf of Samad Al-Shan and a number of villages affiliated with them. The cost of the project, which operates under the design, construction, and financing system, and will enhance the water delivery service to the various residential neighborhoods in the wilayat, is estimated at more than OMR 65 million.
Engineer Ghaleb bin Amer Al-Muslimi, Director of Water Networks in the Wilayat of Al-Mudhaibi, explained that the project is the construction of a water network with a length of 820 km, consisting of excavation works and connecting water connections to homes and residential, commercial, and industrial facilities using polyethylene pipes and wrought iron transmission lines distributed to a number of main sites in the state, in addition to The installation of network booster pumps and emergency shut-off valves distributed on residential plans, in addition to making direct household connections, estimated at more than 11,000 connections that are placed on the main facades of these homes and residential, commercial and industrial facilities; To facilitate the process of connecting water service in the future.
The Director further said, “The project is one of the strategic and vital projects in the Sultanate of Oman, and it is a project that works side by side with the main transmission line project from Al-Sharqiyah South Governorate to the states of Al-Sharqiyah North Governorate.” He added that the water distribution networks project in Al-Mudhaibi covers approximately 90 percent of the residential neighborhoods and villages in the wilayat, starting from the center of the wilayat, Al-Mudhaibi, and a number of nearby villages, all the way to the village of Al-Rawdha, passing through the villages of Samad Al-Shan, Al-Akhdar, and Khadra Bani Difa.
Read More
- 12 expats arrested in Oman for labour and residency violations
- TAS Conclave opens today with Oman’s investment outlook in focus
- Oman energy minister to lead high-profile gathering at 6th TAS Conclave
- Oman International Financial Centre unveils five key regulations to attract global investors
- Oman to launch new tourism routes, digital booking platform
The Oman Water and Wastewater Services Company is seeking to implement a number of future projects in the field of water in a number of wilayats in the North Al Sharqiyah governorate, most notably the water networks project in the wilayat of Dima and Al-Tayyin, where detailed designs and tender documents are being prepared, and the project implementation period is expected to be 26 months, including preparations, and it includes a pumping station in the desert, a conveyor line with a length of 83 km, and 10 distribution tanks with a storage capacity ranging between 2000-10,000 cubic meters.
For all the latest news from Oman and GCC, follow us on Twitter, Instagram and LinkedIn, like us on Facebook and subscribe to our YouTube page, which is updated daily.