Muscat: The project will be implemented through a 35-km submarine cable with a voltage of 132 kilovolts and 60 kilometers of overhead power transmission lines.
The connection will extend from the Mahout substation of 400/33 kilovolts to the Masirah substation.
The transmission line routes, and the marine cable directions have been approved by all relevant authorities, and a tender for project implementation is set to be released, with construction scheduled to commence in 2024.
This project will support all local activities and services on Masirah Island, improve the electricity sector’s infrastructure, and provide sustainable solutions to meet sector needs.
It is worth mentioning that OETC, a member of Nama Group, is the company responsible for the transmission and control of electricity across the country’s network. The electricity is transmitted from production stations to distributed load centers in the governorates.
Read More
- Oman and Russia discuss expanding economic and investment ties
- Oman equestrian forum calls for committee to expand women’s participation
- Faisal Al Rawas puts private sector at centre of second term as Oman Chamber chairman
- Oman’s Al Hoota Cave draws nearly 3,900 visitors during National Day holiday
- Unlicensed fundraising in Oman carries fines of up to RO 1,000, three-month jail term